New Pathway – Chislehurst Road, Lesmurdie

Project Status : Complete
Estimated Completion Date : approx. 25 October 2021
Location : Chislehurst Road from Madera Place to the cul-de-sac, Lesmurdie

Works are scheduled to commence 11 October 2021 for the installation of a new pathway on Chislehurst Road, Lesmurdie from Madera Place to the cul-de-sac linking to the existing pathway.

These works are estimated to take two (2) weeks to complete. The time-frame could vary slightly due to weather conditions and contractor availability. 

Properties located adjacent to the proposed works may experience disturbance to the verge, which may include crossovers, reticulation, and lawns. Any such disturbances will be fully reinstated after the completion of the works. Please contact the City of Kalamunda via the details provided below with any project related matters including complaints or compliments.

The City would like to assure the community, that every effort will be made during these works to minimise impact on those who live nearby and also to the environment.

 