Completed Projects

Filter by:

Project Type
Project Status: Complete
view all projects

Renewal Pathway: Hartfield Road, Forrestfield

Project Status : Complete
Estimated Completion Date : approx. 24 February 2021
Location : between Hartfield Road and Welshpool Road East, Forrestfield

Works are scheduled to commence 17 February 2021, for the renewal of an existing 1.8m wide section of access pathway between Hartfield Road, to Welshpool Road East, near house number 275.

Works are estimated to take one (1) week to complete. This time-frame may vary slightly due to weather conditions and contractor availability.

Properties located adjacent to the proposed works may experience disturbance to the verge, which may include crossovers, reticulation and lawns.  Any such disturbances will be fully reinstated after the completion of the works.

The City would like to assure the community, that every effort will be made during these works to minimise impact on those who live nearby and also to the environment.

Project Images

No images attached

Related Documents

Contact Information

City of Kalamunda
T: (08) 9257 9999
E: enquiries@kalamunda.wa.gov.au 
© City of Kalamunda 2024